| ANR Storage Company |
|
Fifth Revised Sheet No. 15B : Effective |
| FERC Gas Tariff |
|
Supersedes Fourth Revised Sheet No. 15A |
| ANR Storage Company |
RATE SCHEDULE FS
FIRM STORAGE
(Continued)
(i) For biddable releases (less than 1 year):
(1) offers should be tendered by 12:00 p.m. on a Business
Day;
(2) open season ends no later than 1:00 p.m. on a Business
Day(evaluation period begins at 1:00 p.m. during which
contingency is eliminated, determination of best bid is
made, and ties are broken);
(3) evaluation period ends and award posting if no match
required at 2:00 p.m.;
(4) match or award is communicated by 2:00 p.m.;
(5) match response by 2:30 p.m.;
(6) where match required, award posting by 3:00 p.m.;
(7) contract issued within one hour of award posting (with a
new contract number, when applicable); nomination
possible beginning at the next available nomination cycle
for the effective date of the contract. (Central Clock
Time)
(ii) For biddable releases (1 year or more):
(1) offers should be tendered by 12:00 p.m. four Business Days
before award;
(2) open season ends no later than 1:00 p.m. on the Business
Day before timely nominations are due (open season is three
Business Days);
(3) evaluation period begins at 1:00 p.m. during which
contingency is eliminated, determination of best bid is
made, and ties are broken;
(4) evaluation period ends and award posting if no match
required at 2:00 p.m.;
(5) match or award is communicated by 2:00 p.m.;
(6) match response by 2:30 p.m.;
(7) where match required, award posting by 3:00 p.m.;
(8) contract issued within one hour of award posting (with a
new contract number, when applicable); nomination possible
beginning at the next available nomination cycle for the
effective date of the contract. (Central Clock Time)
| Issued by: Dean Ferguson, Vice President |
| Issue date: 10/01/07 |
|
Effective date: 11/01/07 |