| ANR Storage Company |
|
First Revised Sheet No. 16B : Effective |
| FERC Gas Tariff |
|
Supersedes Original Sheet No. 16B |
| ANR Storage Company |
RATE SCHEDULE FS
FIRM STORAGE
(Continued)
Seller is required to meet the Capacity Release
Timeline for processing capacity releases only if
the Releasing Customer's best bid methodology is
either: (1) highest rate, (2) net revenue, or (3)
present value. In all cases, Replacement
Customers will be subject to all requirements of
this Tariff. Storage Service to the Replacement
Customer may commence, prior to the posting of the
winning bid, if capacity has been awarded and a
contract executed.
7.2 EXECUTION OF SERVICE AGREEMENT. Once the provisions of
this Section 7 are satisfied and as a condition
precedent to receiving service pursuant to a capacity
release, Replacement Customer shall execute a Service
Agreement with Seller.
7.3 BILLING ADJUSTMENT. Releasing Customer shall remain
fully obligated under the terms of its Service Agreement
with Seller during any capacity release except for Usage
Charges incurred
| Issued by: Dean Ferguson, Vice President |
| Issue date: 10/01/07 |
|
Effective date: 11/01/07 |