| ANR Storage Company |
|
First Revised Sheet No. 53 : Effective |
| FERC Gas Tariff |
|
Supersedes Original Sheet No. 53 |
| ANR Storage Company |
FORM OF SERVICE AGREEMENT
(For Use Under Seller's Rate Schedule IS)
(Continued)
ARTICLE II
POINT OF INJECTION AND POINT OF WITHDRAWAL
1. Customer shall deliver or cause to be delivered Gas hereunder
at the Point of Injection.
Seller shall Tender to or for the account of Customer,
Equivalent Quantities of Gas stored hereunder, at the Point of
Withdrawal.
ARTICLE III
TERM OF AGREEMENT
1. This Agreement shall be effective for an initial period as of
the date first written above until _____________________, and
__________ to __________ thereafter, until terminated by
Seller or Customer upon __________ prior written notice to the
other specifying a termination date at the end of such period
or any successive period thereafter. The period of service
hereunder shall be from _______________ until the termination
of this Agreement.
ARTICLE IV
RATE SCHEDULE AND CHARGES
1. Each Month, Customer shall pay Seller for the service
hereunder, an amount determined in accordance with Seller's
Rate Schedule IS and the applicable provisions of the General
Terms and Conditions of Seller's FERC Gas Tariff, Original
Volume No. 1 ("Tariff"), as filed with the Commission. Such
Rate Schedule and General Terms and Conditions are
incorporated by reference and made a part hereof. Section VI
and VII of Exhibit A hereto sets forth the applicable
information as follows, which shall be utilized for
transactions hereunder:
a. Rates and Charges
b. Additional charges which are applicable.
| Issued by: Dean Ferguson, Vice President |
| Issue date: 10/01/07 |
|
Effective date: 11/01/07 |