| Cameron Interstate Pipeline LLC |
|
Original Sheet No. 68 : Effective |
| FERC Gas Tariff |
|
|
| Cameron Interstate Pipeline LLC |
GENERAL TERMS AND CONDITIONS
(continued)
(b) All bids submitted during the open season shall be
submitted to Pipeline electronically through the
Pipeline's Internet Web Site. Upon conclusion of the
bidding period, Pipeline shall evaluate the bids in
accordance with GT&Cs Section 4.3.
(c) If Pipeline is willing to accept a bid, Pipeline shall,
no later than 15 days after the close of the bidding
period, notify Shipper of the bid having the highest Net
Present Value ("NPV"). Shipper shall have 10 days after
receiving notice to notify Pipeline as to whether it
will match the bid having the highest NPV and longest
term (up to five years). If the Shipper elects to
exercise its Right of First Refusal to match the bid
with the highest NPV it must execute a new Service
Agreement containing the terms of that bid, which new
Service Agreement shall succeed the prior agreement
following its expiration; provided, however, that
Shipper shall not be required to pay any rate higher
than the maximum applicable rate.
(d) If Shipper does not exercise its Right of First Refusal,
Pipeline may execute a Service Agreement with the entity
submitting the bid with the highest NPV.
(e) If Pipeline receives no acceptable bids on the capacity,
the Shipper may continue to receive service at the
maximum rate for the term elected by the Shipper or such
other rate and/or term as agreed to by Pipeline. A
Shipper who continues service under such basis shall
retain its Right of First Refusal only if the resulting
agreement is a Long Term Service Agreement at the
maximum tariff rate.
4.3 Net Present Value Standard. Pipeline shall award capacity for bids
received during the open season to Shippers that meet Pipeline's
creditworthiness standards set forth in GT&Cs Section 2.5 and whose
bids, based upon Pipeline's determination, have the highest NPV. The
NPV is the discounted cash flow of incremental revenues per
dekatherm to Pipeline produced, lost or affected by the requests for
service and shall be based upon such factors as the term, quantity,
date on which the requested service is requested
| Issued by: |
| Issue date: |
|
Effective date: 11/01/08 |