Top of page top Next Previous


MoGas Pipeline, LLC   Substitue Original Sheet No. 11 : Pending
FERC Gas Tariff Supersedes Original Sheet No. 11
MoGas Pipeline, LLC


   
                        RATE SCHEDULE FT
                  FIRM TRANSPORTATION SERVICE
                          (Continued)
   
2.       Applicability and character of service (continued)
   
     Such service:
   
         (a)  shall be available only to the extent it does not impair Transporter's ability to render service
         under this Rate Schedule and other rate schedules up to the total MDQs Transporter is committed to
         transport under FT Agreements  with all Shipp
   
         (b)  is interruptible; and
   
         (c)  is subject to the rate and charges applicable to Authorized Overrun Service in Transporter's
         Schedule of Rates for Transportation, Original Sheet No. 5, First Revised Volume No. 1 of Transporter's
         FERC Gas Tariff.
   
3.       Rates and charges
   
3.1      Transportation rates:  The applicable rates for service under this FT Rate Schedule are the applicable
maximum Reservation and Commodity Rates shown on the effective Schedule of Rates for Transportation on Sheet No.
5 of this Tariff; provided, ho
   
3.2      New facilities:  If Transporter agrees to construct facilities for service requested by Shipper,
Transporter shall charge Shipper, and Shipper shall pay in advance, 100% of the design and estimated cost,
including an amount representing the incom
   
3.3      Incidental charges:  Subject to Commission approval, Transporter may charge Shipper an amount to
reimburse Transporter 100% of any filing fees or similar fees and, if applicable, sales or use tax that have not
been paid previously by Shipper, whi







Issued by: David J.Ries, President
Issue date: 02/29/08 Effective date: 04/01/08